Client: PT Pupuk Kalimantan Timur

Main EPCM Consultant: Meinhardt Indonesia

Project: Sewage Treatment Plant

Location: West Papua, Indonesia

GIE Scope of Work:
Delivered comprehensive Detail Engineering Design services for the Sewage Treatment Plant, covering the process design basis, influent and effluent specifications, process flow development, and detailed engineering calculations.

The design covered all major treatment units, including the Grease Trap, Equalization Tank, Aeration System, Sedimentation Tank, Chlorination System, Sludge Treatment System, and Multimedia Filters. All engineering documents and calculations were completed and submitted under IFR and IFA status, finalizing the detailed engineering scope for the complete STP system.

Leave a Reply

Your email address will not be published. Required fields are marked *